Building Update
While it might look like nothing is going on with our building renovation, things are happening. Final design drawings should be ready for the contractor soon. The contractor will use those drawings to create a final budget. The structural engineer was on site last week and will prepare a plan for removing the load-bearing side walls on the upper floor which will become the sanctuary. Electricians installed an electrical feed and brush has been cleared out behind the building. A new sign has been placed along the street announcing our plans, and we’ve had some positive response from the community about it. Also talks with the bank are ongoing to create a financial plan that saves as much interest cost as possible. At this point, we are hoping demolition can begin in February. Once demolition starts, we’ll begin posting some potos on the HOME portion of the River City website. If you have any questions, see David Cornett.